Monte Rio Bridge Retrofit

Upcoming Public Open House

Sonoma County invites the community to learn about the proposed seismic retrofit, meet the project team, ask questions and share input.

Tuesday, November 10, 2026
5:00–7:00 p.m.
Monte Rio Recreation & Park District
20488 Highway 116, Monte Rio, CA 95462

Public Comment Opportunity: Beach Access and Recreation
Comments accepted through December 10, 2026

Sonoma County is seeking public input on a proposed Section 4(f) finding related to temporary construction impacts at Big Rocky Beach and Sandy Beach, including recreational access and parking.

Review the draft documentation and share your comments by December 10. Comments may also be provided at the November 10 community open house.

Review the Section 4(f) Documentation and Learn How to Comment

What's Happening

Sonoma County is moving forward with a seismic retrofit of the existing Bohemian Highway Bridge over the Russian River in Monte Rio. The project would strengthen the bridge with new supports and connections to reduce the risk of collapse during a major earthquake while retaining the bridge’s existing size and overall appearance. 

Construction is currently anticipated to begin in summer 2028 and last approximately four to six months. The bridge would close to traffic during construction, with vehicles detoured via Moscow Road and State Route 116. The full detour is approximately 7.35 miles and is expected to add about 15 minutes of travel time, depending on traffic conditions. The schedule is preliminary and may change as design and construction planning advance. 

The County is developing plans to maintain access to homes, businesses and recreational areas whenever possible and will coordinate with emergency services, transit providers and other affected services before construction. 

Public Comment Opportunity: Section 4(f) Review

Comments due December 10, 2026

Sonoma County is seeking public comments on a proposed de minimis impact finding under Section 4(f) of the U.S. Department of Transportation Act as part of the Bohemian Highway Bridge Seismic Retrofit Project.

Section 4(f) protects publicly owned parks and recreational areas from adverse impacts associated with federally funded transportation projects. A de minimis finding means the project would not adversely affect the recreational activities, features, or attributes of the protected property after measures to avoid, minimize, or mitigate impacts are considered.

What does this mean for beach access?

Construction would temporarily affect portions of Big Rocky Beach and Sandy Beach, which are managed by the Monte Rio Recreation and Park District.

Most work would take place near the existing bridge abutments, away from the primary beach-use areas. Beach access is expected to remain available during construction, except in designated work and safety areas. Approximately 30 parking spaces at Big Rocky Beach would be temporarily unavailable.

Based on these anticipated impacts and measures to minimize disruption, the County is proposing a Section 4(f) de minimis impact finding.

Review the documentation

Read the Draft Section 4(f) Memorandum

How to submit comments

The public is invited to review the proposed finding and provide comments about potential impacts to recreation and beach access.

Public comment deadline: December 10, 2026.

All comments received during the public comment period will be considered before the Section 4(f) determination is finalized.

How We Got Here

The County previously studied replacing the Bohemian Highway Bridge with a new, wider bridge that would have included bicycle and pedestrian improvements. That project was discontinued in 2023 after estimated construction costs increased to more than $80 million and available seismic retrofit funding would have left a substantial funding gap. 

Caltrans recommended instead retrofitting the existing bridge. The current project is estimated at approximately $4.6 million in construction costs and addresses the primary seismic safety need with a smaller construction footprint and a significantly shorter construction period than the previous replacement project. 

Why It Matters

The Bohemian Highway Bridge was built in 1934 and does not meet current seismic design standards. Engineering analysis identified vulnerabilities that could increase the risk of collapse during a major earthquake. 
The proposed retrofit would:

  • Improve seismic safety and reduce the risk of bridge collapse.
  • Strengthen and retain the existing bridge.
  • Preserve its overall appearance and roadway configuration.
  • Reduce the construction footprint and duration compared with the previous replacement project. 

Community Outreach

Community input received during planning for the previous bridge replacement remains part of the project record and continues to inform the County’s understanding of community concerns. Because the project has changed substantially from replacement to retrofit, the community will have new opportunities to learn about the current project and provide input.

Upcoming Public Open House

Tuesday, Nov. 10, 2026 | 5–7 p.m.
Monte Rio Recreation & Park District
20488 Highway 116, Monte Rio

Meet the project team, learn more about the proposed seismic retrofit, ask questions and share your input.

The County is accepting public comments on the proposed Section 4(f) de minimis impact finding for temporary effects on recreational areas near the bridge, including Big Rocky Beach and Sandy Beach. Review the documentation in the Public Comment Opportunity: Section 4(f) Review section above and submit comments by December 10, 2026.

Frequently Asked Questions


What is the Bohemian Highway Bridge Seismic Retrofit Project?

The project would strengthen the existing Bohemian Highway Bridge over the Russian River to reduce the risk of collapse during a major earthquake. Rather than constructing a new bridge, the project would retrofit the existing bridge with new structural supports and connections.

Why is this project needed?

The bridge was constructed in 1934 and does not meet current seismic design standards. Engineering analysis identified vulnerabilities that could increase the risk of collapse during a major earthquake. The proposed retrofit would strengthen the bridge to improve seismic performance and protect public safety.

Why did the project change from replacement to retrofit?

The previous project proposed replacing the existing bridge with a new bridge. As the project advanced, the estimated construction cost increased to more than $80 million. The bridge replacement project would only have been eligible for limited funding through the Caltrans Seismic Retrofit Program, leaving a substantial funding gap that the County does not have available to construct the replacement project.

As a result, the bridge replacement project was discontinued, and Caltrans recommended a seismic retrofit of the existing bridge. The current retrofit is estimated at approximately $4.6 million in construction costs, substantially less than bridge replacement, while addressing the primary goal of reducing the risk of bridge collapse during a major earthquake.

What is the difference between the old bridge project and the current project?

The previous project proposed replacing the existing Bohemian Highway Bridge with a new bridge located just west of the existing structure. The new bridge would have included a wider roadway and new bicycle and pedestrian facilities, and construction was anticipated to occur over approximately three construction years. That replacement project was discontinued in 2023.

The current project would retain the existing bridge and seismically retrofit it to reduce the risk of collapse during a major earthquake. The current project has a smaller construction footprint and is anticipated to take approximately four to six months to construct. The existing bridge cross section would remain substantially unchanged, meaning the wider bicycle and pedestrian improvements proposed as part of the previous project are not part of the current retrofit project.

Why is environmental review being revisited if an environmental document was already completed?

Because the project has changed from a bridge replacement to a smaller seismic retrofit, Caltrans and Sonoma County are revalidating the existing environmental documents to confirm they remain applicable to the revised project. A new environmental review is not anticipated. However, certain topics, such as Section 4(f) and community impacts, will be updated as needed to reflect the current project.

What happened to the community input and outreach completed for the previous bridge replacement project?

The community provided input during the development of the previous bridge replacement project, including feedback that informed the alternatives considered at that time. For example, the 2020 bridge alternatives analysis notes that a public survey showed a preference for a steel arch bridge over a steel truss bridge.

Information obtained through the previous outreach remains part of the project record and continues to inform the County’s understanding of community concerns. The previous outreach focused on a replacement bridge, including concepts such as wider bicycle and pedestrian facilities. Those improvements are not part of the current seismic retrofit project.

The current project is also using previous environmental studies and information about community and recreational resources as part of the re-evaluation of the revised project. However, because the project has changed substantially, the proposed environmental findings for the current retrofit will have a new opportunity for public review and comment before they are finalized.

Is the County still replacing the bridge?

No. The previously proposed bridge replacement project was discontinued in 2023. The current project would retain and seismically retrofit the existing bridge.

What improvements would be made to the bridge?

The proposed work includes:

  • New reinforced-concrete support structures behind both bridge abutments
  • Strengthening existing steel connections
  • New steel ties connecting bridge spans
  • New ties between the bridge and the supports behind the abutments
  • Extensions to the bridge seats at both bridge abutments
  • Cable restrainers connecting the bridge superstructure and piers
  • Restoration of pavement and embankment disturbed during construction 
Will the bridge look different after construction?

The current project is a retrofit of the existing bridge, rather than construction of a new bridge. The existing bridge cross section would remain, and the approach roadway work would be limited to the existing roadway width. The bridge would substantially retain its existing overall appearance and roadway cross section.

Will the bridge have to close during construction?

Yes. The bridge is anticipated to close to traffic during construction, which is currently expected to last approximately four to six months. During the closure, traffic would be detoured via Moscow Road and State Route 116.

The project team is developing a Traffic Control Plan to minimize disruption and maintain access to nearby homes and businesses. The County will also coordinate with fire, law enforcement, ambulance, transit, and other service providers before construction to plan for emergency response and temporary transportation changes.

What will the detour be and how much additional time should drivers expect?

Vehicles would be detoured using Moscow Road and State Route 116 while the Bohemian Highway Bridge is closed. The current detour map identifies the full route as approximately 7.35 miles. The full detour route is expected to add approximately 15 minutes of travel time, depending on traffic conditions.

Monte Rio Bridge Detour Map

How long will construction last?

Construction is currently anticipated to begin in summer 2028 and last approximately four to six months. The schedule is preliminary and may be refined as design and construction planning advance.

What happens to River Boulevard, Main Street and Bohemian Highway?

Construction of the new support structure behind the southern end of the bridge would require a temporary closure of the River Boulevard/Bohemian Highway/Main Street intersection for approximately one to two months. During this period, local traffic would be detoured via Bohemian Avenue, Bohemian Highway, Fir Road and Main Street.

The project team is working to minimize disruption and maintain continuous access to nearby homes and businesses, subject to temporary traffic controls. Additional details about the intersection closure, traffic management and construction phasing will be refined as design progresses.

Will residents and businesses still be accessible?

The current traffic planning calls for continuous access to businesses and residences, subject to temporary traffic controls and the temporary intersection closure associated with work at the southern abutment.

What about emergency services?

Before construction, the County will coordinate with fire, law enforcement, ambulance and other emergency-response providers regarding the bridge closure, detour routes, construction schedule and incident response procedures. The Traffic Control Plan developed for construction will identify emergency-response routes and communication procedures.

What will happen to bus service?

Sonoma County Transit routes serve the Monte Rio area. Because the bridge would be closed, temporary rerouting or stop relocation may be necessary. Final arrangements would be coordinated with Sonoma County Transit and documented in the Traffic Control Plan.

Can pedestrians and bicyclists cross the bridge during construction?

While the bridge will be closed to vehicle traffic during construction, the project team is focused on maintaining safe pedestrian and bicycle access where feasible. The sidewalk is expected to be intermittently closed for approximately one to two months to accommodate construction activities. During these closures, temporary access and traffic-control measures will be developed to minimize disruptions to pedestrians and bicyclists.

Will the beaches remain open?

Public access to the river and beach areas will be maintained during construction, except within designated construction, staging and safety exclusion areas.

Big Rocky and Sandy Beaches would experience temporary construction-related use, with fencing, barriers, signage or similar measures separating construction and public-use areas. Dutch Bill Creek Beach is not proposed for construction access or staging.

What areas would be temporarily affected?

Temporary construction activity is currently anticipated at portions of Big Rocky Beach and Sandy Beach, as well as the River Boulevard and Main Street site. Koret Park, Riverfront Meadow and the Rio Theater are not proposed for construction, staging or access use under the current project.

Will the Monte Rio Fishing Access remain available?

The current proposal would use existing paved circulation areas at the Monte Rio Fishing Access as a temporary contractor access route. No staging, material storage, equipment parking, grading or permanent construction is proposed there. Recreational access is intended to remain available.

Will parking be affected?

Yes. Approximately 30 parking spaces in the Big Rocky Beach Parking Lot are anticipated to be temporarily unavailable during construction. The County is coordinating measures to maintain recreational access, with parking details to be refined as staging plans are finalized.

Will construction be noisy?

Yes. Construction will temporarily generate noise from activities such as pile installation, concrete work, grinding, and temporary shoring. Much of the construction will occur near the bridge abutments, set back from the beach areas, so noise impacts are expected to be concentrated near these work areas.

Most construction activities are anticipated between 7:00 a.m. and 7:00 p.m., with no work on holidays and limited weekend work between 9:00 a.m. and 5:00 p.m. with prior approval. No permanent noise changes are anticipated after construction is complete.

Will the project add bike lanes or wider sidewalks?

No, not under the current project scope. The retrofit would retain the existing bridge cross section. Bicycle and pedestrian improvements presented during earlier community workshops were associated with the discontinued bridge replacement project, not the current seismic retrofit.

What happens to the bridge after construction?

The existing bridge would remain in place with its current general roadway configuration. The retrofit is being designed to reduce the risk of collapse during a major earthquake.

Will the public have an opportunity to comment?

Yes. The County will provide opportunities for the community to learn more about the current seismic retrofit project, including a public open house where community members can learn about the project, ask questions, and share input with the project team. Project information and updates will also be made available through the project website as the project progresses.

The draft Section 4(f) documentation is now available for public review. The proposed finding addresses temporary construction impacts to Big Rocky Beach and Sandy Beach, including beach access and parking.

Community members are encouraged to review the documentation and submit comments by December 10, 2026. Comments may be emailed to Samuel.Baumgardner-Kranz@sonomacounty.gov or shared at the November 10 community meeting.

See the Public Comment Opportunity: Section 4(f) Review section above for additional details and the document link.


Additional Resources

  • Detour Map
  • Public Meeting Materials (Coming Soon)
  • Environmental Documents (Coming Soon)
  • Project Documents (Coming Soon)

Stay Informed

Want project updates delivered to your inbox?
Join the Monte Rio Bridge Retrofit Project distribution list by emailing EngagePI@sonomacounty.gov and put Monte Rio Bridge in the subject line.

Contact

Samuel Baumgardner-Kranz, Sonoma Public Infrastructure: samuel.baumgardner-kranz@sonomacounty.gov